What it means
A new office can have installed air conditioning that turns on yet fails to maintain the required temperature across all floors, so commissioning tests the system under defined conditions and records whether it meets requirements. Merely seeing equipment run is not enough.
The Whole Building Design Guide describes commissioning documents as a record of key project decisions and performance criteria across phases, emphasising owner requirements, team responsibilities, acceptance and use after occupancy, which supports a process broader than a single final inspection. Define the owner's requirements first, with temperature, ventilation, power resilience and maintenance needs made measurable, because otherwise the team has no clear acceptance target.
Set a commissioning plan listing systems, roles, tests, dependencies, timing and documentation that matches the project's actual scope. Review design by comparing drawings and specifications with owner requirements before installation, since a design error found early is easier to correct.
Coordinate disciplines, because controls, electrical equipment and mechanical systems interact and a test of one component alone may miss a failure when systems run together. Inspect installation to check that equipment, wiring, sensors and labels match approved specifications, since functional tests cannot cure missing parts, and use prefunctional checks to verify calibration, connections, safety settings and manufacturer start-up before demanding full performance.
Run functional tests of how a system responds to normal load, failure and changeover conditions where relevant, recording conditions and actual results. Consider life safety separately, because fire and emergency systems may have specific statutory inspections that commissioning work does not replace.
Document faults in an issue log naming the failure, location, owner and status, since a verbal promise to repair is not a closed test, and retest after correction, because a changed sensor or control program can fix one issue and create another. Check seasonal conditions too, as heating or cooling performance may not be testable under the weather at handover, so plan deferred tests and assign responsibility.
Train operators and deliver documentation, because a working system can fail in use if staff do not know alarms, schedules or maintenance needs, and as-built information, test results, manuals and settings help the facilities team operate the asset. Clarify acceptance, since the owner, contractor and commissioning provider may have different roles, and state who signs each document and what unresolved issues remain.
Budget time, because testing can reveal corrections that affect the schedule and a handover date should not erase critical open faults, and make sure operators have the passwords, permissions and instructions needed for lawful operation while keeping security-sensitive details protected. Separate commissioning from snagging, since a snag list can capture visible defects such as finishes while commissioning focuses on verified system performance, and both may be needed.
Avoid treating a pass rate as quality alone, because first-time pass rate shows testing outcomes but rushed or easy tests can inflate it, so review coverage and severity and track critical issues, where a minor label error differs from failure of emergency power. Include a post-occupancy review, know the contract because requirements, warranties and responsibility for defects depend on project documents and local rules, and measure owner outcomes such as energy use, comfort complaints and equipment reliability, which supplement rather than replace formal acceptance tests.
In practice
Real-world examples.
Example
A controls test checks whether backup power starts and critical equipment changes over. The team simulates a mains failure and records the time each system takes to restore. Any equipment that does not restart goes on the issue log for correction and retest.
Example
Air-conditioning readings reveal an unbalanced floor before occupants move in. The engineers adjust dampers and control settings, then repeat the readings. The retest confirms that every zone meets the specified temperature range.
Example
A winter heating test is scheduled after a summer handover and remains an open item. The report names who is responsible for running the test and when. The owner keeps the item open until the results are recorded.
Formula
Calculation
Optional first-time test pass rate = tests passing on first attempt / valid tests performed x 100.
Worked example. If 45 of 50 tests pass on the first attempt, the rate is 45 / 50 x 100 = 90%. If four of the five failures then pass after correction and retesting, 49 of 50 tests have passed eventually, which is 98%. Neither figure shows whether the remaining failure is minor or safety-critical.Case study
Seen in the real world.
Entirely fictional case: Falcon Offices found inconsistent cooling during functional testing. The team corrected control settings, retested the affected areas and handed operators the final sequences and open seasonal-test schedule. The case does not assume all defects are eliminated or that a test result substitutes for statutory approval.
Falcon also used a separate commissioning provider to review coordination between the controls contractor and the electrical contractor. Because the provider's independence was defined and resourced in the contract, the review found a wiring label error early and flagged it before testing. The owner treated the exercise as a way to reduce uncertainty about whether the building would operate as promised, with its value found in traceable requirements, meaningful tests and completed follow-up.
Watch out
Common mistakes.
- Starting only at handover without clear owner requirements.
- Closing a fault after a repair without retesting.
- Reporting a high pass rate while critical failures remain unresolved.
Questions
People also ask.
What is commissioning?
A documented process for verifying that systems meet defined owner and design requirements.
Who does it?
A project team including owner, designers, contractors, operators and sometimes a specialist provider.
When does it happen?
It should begin with requirements and continue through design, installation, testing and needed follow-up.
From the founder's library

Take it further with the book.
Build your financial confidence beyond this definition. Shihan's full-length guide, Accounting Fundamentals, takes the same plain-English approach and turns it into a complete, practical playbook for non-finance managers, business owners and students - with chapter-end quiz answers and presentation slides included.
25% off with code MMHQ25, applied at checkout. Priced in USD - checkout may show the equivalent in your local currency.
View the book and save 25%