Back to Glossary

Cost to Complete

Cost to complete is the current estimate of spending still needed to finish an agreed project or work package. It covers remaining work from the estimate date, not the money already spent. Add it to actual costs to date to obtain an estimate at completion; compare that forecast with the approved budget after checking scope and assumptions.

From the Money Master HQ dictionary, founded by Shihan Sheriff (FCMA, VP of Finance at Nomod, CFO at Esanjo Ventures). How these definitions are written.

What it means

A contractor has spent much of a project budget but still has several deliverables unfinished, so the original budget is not a reliable answer to what remains and cost to complete asks for a fresh estimate of resources needed for the outstanding work. Oracle describes estimate to complete (ETC) as the estimated cost of finishing an activity, with different calculation methods available in its project system, and PMI distinguishes ETC, the remaining expenditure, from estimate at completion (EAC), the forecast total.

These are related but not interchangeable. Start with a dated scope of remaining tasks, because a percentage of work completed is not enough if the expensive tasks are still ahead.

Estimate labour hours, materials, subcontracting, testing, delivery and closeout work still needed, and include committed costs not yet recorded as actuals under the project's accounting convention without counting the same purchase twice, reviewing open purchase orders, accruals and invoices to reconcile the cost-to-date number. Use current prices rather than simply repeating the rates in the original bid if those rates have changed.

As an illustration, actual cost to date is $1.2 million and estimated remaining cost is $0.8 million, so forecast total cost is $2.0 million. If the approved budget is $1.8 million, the forecast exceeds it by $0.2 million, but a forecast overrun is not automatically an authorised budget increase.

Separate remaining cost from remaining budget, since budget left is an authorisation limit, not proof the work can be finished for that amount. A manual bottom-up estimate may be best when scope or productivity has changed materially, while a formula based on historical cost performance may be useful for another situation, and the assumption behind the method should be stated because a continuation of current inefficiency leads to a different estimate from a plan that fixes it.

Earned value methods can combine completed work and cost trends to estimate the remainder, but their results depend on reliable baselines. Completion percentage can be misleading if measured by spending, since spending 70% of the budget does not mean 70% of the work is done.

Track approved changes so that new scope is shown separately from an overrun on the original scope, and document excluded or uncertain work because hidden commissioning and handover tasks can make a forecast falsely optimistic. Ask suppliers for updated quotes where major packages remain, since a stale quote is not a current commitment, and include contingency based on identified uncertainty without burying a known cost in a vague reserve.

A risk register can record threats to the estimate and the response owner but should not substitute for costing the base work, and work that fails acceptance criteria must be redone, so rework belongs in the remaining cost. Reforecast at key milestones or when a material scope, price or schedule change occurs, and keep the estimate date visible, since a forecast made months ago may no longer guide a decision.

Compare ETC with available cash and contractual payment timing, as a project can be profitable on paper but need funding before final payment, and coordinate time and cost forecasts because a schedule delay can raise staff and site costs even if materials are unchanged. For a portfolio, add component remaining costs only after resolving shared resources and inter-project dependencies, avoid using a single percentage for all work packages when their risk and cost mix differ, and explain what changed between forecasts (quantity, price, productivity, scope or contingency), because the result supports an early decision to adjust scope, resources or funding but is not an accounting promise that the exact final cost is known.

In practice

Real-world examples.

1

Example

Actual cost is 1.2 million and ETC is 0.8 million, giving a 2.0 million forecast against a 1.8 million budget.

2

Example

A supplier revises its quote, raising the cost still needed even though past spending does not change.

3

Example

A team discovers handover testing was omitted and adds it to its remaining-work estimate.

Formula

Calculation

Estimate at completion = actual cost to date + cost to complete. A model-based ETC can use remaining budgeted work adjusted for expected cost performance, but assumptions must be stated.

Case study

Seen in the real world.

This entirely fictional case follows West Quay Builders. Its monthly report showed a healthy remaining budget, but testing and specialised labour were still outstanding. A bottom-up estimate raised ETC. Managers flagged the expected overrun early and sought a documented decision on scope and funding. The case is invented.

Watch out

Common mistakes.

  • Equating unspent budget with the true cost of unfinished work.
  • Assuming percent of budget spent equals percent of work completed.
  • Double-counting committed purchases as both actual and future cost.

Questions

People also ask.

Is cost to complete the same as final cost?

No. Add actual cost to date to estimate final cost.

Can ETC change?

Yes. Scope, prices, productivity and risk change as work proceeds.

Should a forecast overrun change the budget?

Not automatically. Budget changes require the applicable approval process.

Was this explanation helpful?

From the founder's library

Accounting Fundamentals: A Non-Finance Manager's Guide to Finance and Accounting, by Shihan Sheriff

Take it further with the book.

Build your financial confidence beyond this definition. Shihan's full-length guide, Accounting Fundamentals, takes the same plain-English approach and turns it into a complete, practical playbook for non-finance managers, business owners and students - with chapter-end quiz answers and presentation slides included.

US$2.24US$2.99

25% off with code MMHQ25, applied at checkout. Priced in USD - checkout may show the equivalent in your local currency.

View the book and save 25%
Last updated · October 8, 2026
Browse all terms →

Disclaimer

The information provided in this finance dictionary is for educational and informational purposes only. It should not be construed as financial, investment, legal, or tax advice. Always consult with a qualified professional before making any financial decisions. Money Master HQ makes no representations or warranties about the accuracy, completeness, or suitability of this information. Use of this content is at your own risk.