What it means
A client may care who supplies a complex lift, facade or control system, so rather than letting the main contractor choose freely, the contract may provide for a specialist to be nominated. The contractor then coordinates that firm's work with the rest of the project, and the nomination process and obligations should be read in the chosen contract form.
FIDIC's discussion of nominated subcontractors explains different approaches to allocating risk on international projects, while JCT's subcontract guide shows that other standard forms use distinct categories and documents. These are references, not one global rule, so a project should not copy a statement about FIDIC into a different contract without checking its terms.
The client or its consultant may select a preferred specialist for technical quality or continuity with a design, which can reduce the contractor's freedom to negotiate price, programme or warranties. The main contractor still needs workable terms with the specialist, because nomination should not replace due diligence.
A nomination instruction should identify the work, price basis, design responsibility, schedule and required subcontract terms, and if the specialist's offer excludes testing or maintenance documents, the gap must be addressed before award. Ambiguous interfaces are a common source of delay and claims.
Some contracts allow the contractor to object on specified grounds, such as inadequate capacity or unwillingness to accept required liabilities, with notice periods and evidence requirements, so a contractor should raise an objection promptly and precisely because silence can have consequences under a particular form. Risk does not always sit in one place: the main contractor may remain responsible to the client for coordination and some subcontract performance, while nomination can create special relief or indemnity mechanisms.
The actual balance depends on the contract wording and facts, and "the client chose them" is not a full legal defence. Payment flows should be clear, as the client may certify an amount for the specialist through the main contract while the contractor pays under its subcontract, and some forms include provisions addressing proof of payment or direct payment in limited circumstances, so do not assume the client automatically pays the specialist or that the contractor has no cash-flow exposure.
Programme coordination is essential, since a nominated lift installer may need a finished shaft, power supply and site access by specific dates, and the main contractor should integrate those dependencies into the main programme. Delays caused by the specialist, client instruction or other trades can have different contractual treatment.
Design responsibility also needs a boundary, as a facade specialist might design fixings while the client's architect designs the overall concept, so record who approves calculations and who is responsible for performance, because an approval stamp from a consultant does not necessarily transfer all design risk. Compare a nominated subcontractor with a domestic subcontractor chosen by the main contractor, where the contractor usually has more choice and control over procurement.
In a nominated case the selection route can affect objections and risk allocation, yet both still require a functioning subcontract and coordinated site management, and neither should be confused with a direct contract between client and specialist, since a separately appointed specialist may be a direct contractor, not a subcontractor at all. A nominated subcontractor can give the client influence over specialist selection, but responsibilities do not vanish, so check the nomination procedure, objection grounds, subcontract terms, payment and design interfaces, show the contractual chain on a simple diagram before work begins, and keep written records of instructions and approvals, because the contract, not the label alone, decides the risk allocation.
In practice
Real-world examples.
Example
A client designates a lift supplier through the main construction contract. The contract names the supplier and sets out how its price is included in the main contractor's sum. The contractor signs the subcontract and coordinates the installation with the structure.
Example
The contractor checks whether the nominated facade firm can meet the programme. It asks for the firm's production schedule and compares it with the dates the scaffold and structure will be ready. Any gap is raised in writing before the subcontract is signed.
Example
A specialist's testing scope is agreed before the subcontract is signed. The contractor insists that commissioning tests, certificates and maintenance manuals are written into the scope. This avoids an argument at completion about who pays for them.
Formula
Calculation
No universal nomination-risk formula exists. Illustrative package share = specialist package value / main contract price x 100. Example: $2,000,000 / $20,000,000 = 10%. This does not measure critical-path importance or legal responsibility.
A small package can matter more than its share suggests: if the lift installation is 10% of the price but gates the fit-out of every floor, a delay in it can hold up work worth far more than $2,000,000. Share of price is only a starting point for the risk discussion.Case study
Seen in the real world.
This illustrative and entirely fictional case follows Harbor Tower, an invented office project. The client nominates a lift specialist; the main contractor checks its schedule and asks how power and shaft access will be provided. They record interfaces and subcontract payment terms before signing.
The case does not claim the client or contractor always bears a particular default risk. When the shaft is handed over a week late, the contractor notifies the client promptly and records the effect on the lift programme, using the interface record agreed earlier. The conversation focuses on what the contract says about that delay, not on who chose the specialist.
Watch out
Common mistakes.
- Assuming client nomination releases the main contractor from all responsibility.
- Failing to align the specialist's scope, programme and payment terms with the main contract.
- Treating a direct client contract or a named subcontractor as legally identical to a nominated subcontractor.
Questions
People also ask.
What is a nominated subcontractor?
A specialist selected through the client's contract process for the main contractor to subcontract.
Why nominate?
The client may want a specific specialist for design, quality or continuity reasons.
Who bears the risk?
It depends on the main contract, subcontract and facts; nomination does not automatically shift every risk.
From the founder's library

Take it further with the book.
Build your financial confidence beyond this definition. Shihan's full-length guide, Accounting Fundamentals, takes the same plain-English approach and turns it into a complete, practical playbook for non-finance managers, business owners and students - with chapter-end quiz answers and presentation slides included.
25% off with code MMHQ25, applied at checkout. Priced in USD - checkout may show the equivalent in your local currency.
View the book and save 25%