What it means
A project manager expects a specialist team to spend much of next month on approved work, and project resource forecast utilisation compares scheduled demand with available capacity for that period. It is a forward-looking planning ratio, not proof that employees will work those hours or that the project will succeed.
Start with the horizon, since a weekly view can reveal a bottleneck hidden by a smooth quarterly average, and show the calendar dates and update frequency. Choose the resource type, because people, equipment and facilities have different units and a single percentage should not mix a person's hours with machine hours.
Define available capacity by subtracting known leave, holidays, training and agreed non-project obligations from nominal working hours when the denominator is intended to mean deployable hours, and use the resource calendar, since an engineer may be available for only part of a week and location, shift and working-day differences affect timing. Account for ramp-up too, as a new hire or contractor may not be fully productive immediately, and availability is not the same as deployable proficiency.
Define forecast demand by including estimated hours for approved project tasks and explaining whether tentative opportunities are included as a separate scenario, and separate committed from tentative work, since a 95% load made mostly of unapproved proposals is less certain than one built from signed projects. Include non-project work, because support rotation, maintenance, management and recurring meetings consume hours even if they do not appear on a project plan.
Trace each demand estimate to a named project and activity so the team can challenge changed scope, and refresh actual progress by updating remaining hours when an activity finishes early or is delayed, rather than carrying stale effort forward. Match skills, because ten open hours from a different specialist do not cover a requirement for a scarce certification, so report the ratio by capability as well as by team, and recognise shared bottlenecks, since a laboratory, vehicle or approval officer can constrain a task even when the project team has spare labour hours.
Check assignment conflicts by reconciling portfolio demand, as the same person may appear on two project plans, and avoid false precision, since an early-stage estimate is uncertain and a range or scenario is better than presenting a fractional hour as a commitment. Assess peaks too, because an average utilisation of 75% for a month does not help if one week requires 140% of capacity.
Set an operating target with care, since aiming for 100% of every deployable hour leaves no room for rework, handovers or unpredictable issues, and the right buffer depends on the work. APM explains that levelling can move work to fit limited resources and may extend the schedule, while smoothing uses available float without changing the overall duration.
Compare options, as reprioritising work, moving a noncritical task or adding qualified capacity can relieve an overload, but each has cost or schedule effects. Do not confuse planned and actual utilisation, since actual timesheets describe recorded effort while the forecast estimates future allocation under assumptions.
Show assumptions with the number by listing the calendar, capacity exclusions, project probability and skill grouping so another manager can reproduce the estimate. Escalate a constrained period early, because a forecast above available capacity is a planning conflict, not an instruction to work extra hours.
In practice
Real-world examples.
Example
A design team has 200 deployable hours next week and approved tasks need 160 hours, giving 80% forecast utilisation.
Example
A monthly average of 80% masks a week at 120%, so the project manager moves a noncritical task.
Example
One certification holder is fully allocated even though the wider team has spare hours; a team average would hide the bottleneck.
Formula
Calculation
Illustrative forecast utilisation = scheduled project hours for the chosen resource and period / deployable hours for that resource and period x 100. If 180 of 225 deployable hours are planned, the forecast is 80%. Show tentative demand and non-project commitments separately or state their treatment.Case study
Seen in the real world.
This entirely fictional case follows Cedar Projects. A quarterly chart suggested the design team had room for a new assignment. Its weekly skill-level view showed that two critical weeks required more hours from one approved designer than were available. The manager shifted a flexible review task and requested a revised client schedule rather than assuming overtime. The forecast was a planning aid, not a guarantee of delivery.
Watch out
Common mistakes.
- Using nominal paid hours without accounting for known leave or recurring work.
- Averaging away a weekly or skill-specific overload.
- Treating tentative sales opportunities as firm commitments without labelling the scenario.
Questions
People also ask.
Is 100% utilisation the ideal target?
Not automatically. A useful buffer depends on rework, interruptions and the type of work.
Is it a timesheet metric?
No. It forecasts future demand; actual time records are a separate measure.
Can a forecast exceed 100%?
Yes, as a signal that planned demand exceeds stated capacity, not as proof it can be delivered.
From the founder's library

Take it further with the book.
Build your financial confidence beyond this definition. Shihan's full-length guide, Accounting Fundamentals, takes the same plain-English approach and turns it into a complete, practical playbook for non-finance managers, business owners and students - with chapter-end quiz answers and presentation slides included.
25% off with code MMHQ25, applied at checkout. Priced in USD - checkout may show the equivalent in your local currency.
View the book and save 25%Related
