What it means
A software customer expects its first live transaction by June 15, and the team finishes configuration on June 12 but data testing ends June 22, so the milestone is seven days late if live operation was the agreed endpoint. Define each milestone in observable terms, because "almost ready" or "implementation complete" can mean different things to sales, technical staff and the customer, and specify evidence for completion.
An illustrative slippage in calendar days is the actual milestone completion date minus the original agreed target date, so June 22 minus June 15 is seven days late, recorded as +7. Atlassian describes a project baseline as a fixed reference for scope, schedule and cost, and comparing actual milestones with that baseline exposes movement that a constantly updated plan would hide.
Asana's client-onboarding template illustrates breaking onboarding into assigned work and stages, but an internal task marked done does not necessarily prove the customer-facing milestone was achieved. Record the original target and the revised forecast separately, so that a mutually agreed later date may become the operational plan while the historical original target remains visible for learning.
Identify dependencies, since customer data, security approval, access and vendor integration may each determine the finish date, and record who must provide what and when. Avoid reflexive blame, because a delayed customer input can be caused by unclear instructions from the delivery team, while an internal delay can reflect a genuine scope change, so investigate the chain.
Track an at-risk milestone before it becomes late, escalating and agreeing a response while there is still time if a prerequisite due tomorrow remains unavailable. Measure both days and incidence, since the average slippage can be dominated by one extreme case, so show the median, late share and the number of active milestones.
Consider business impact, as a seven-day delay to a trial account and to a critical revenue launch may have different consequences, so pair schedule variance with severity. Check milestone sequencing, because one slipped data import can delay training and go-live, and each downstream delay should not be counted as an independent root cause without noting their common dependency.
Protect the customer promise, since an internal project calendar can shift without the customer being informed, and a revised customer commitment needs the appropriate communication and approval. Keep uncompleted items visible, because completed-only slippage reports exclude milestones now overdue but still open, so show their current lateness and expected finish separately.
Distinguish planned buffer from slippage, as a team may include contingency between an internal completion target and a customer commitment, and report which baseline the metric uses. Watch product mix, since new integrations or enterprise security steps may take longer than a standard self-serve onboarding, so compare similar cohorts, and review scope changes, which should follow the authorised change process because a task board note cannot change the agreement alone.
Link to adoption, because hitting dates does not prove the customer can use the product effectively, and use retrospectives, since repeated slippage from data-quality checks may justify clearer prerequisites, earlier validation or more realistic promise dates. Keep dates in the customer's local calendar when that is how the promise was made so a time-zone conversion near midnight does not create a false one-day miss; for an owner, slippage shows whether customers reach the promised points on time and why not, and is a planning and relationship measure, not just a score against the delivery team.
In practice
Real-world examples.
Example
A June 15 go-live target finishes June 22, creating seven days of slippage. The report keeps the June 15 baseline even though the customer agreed to wait. The cause is recorded as late data validation.
Example
An overdue but incomplete milestone remains in the report. A training session planned for the first of the month has not happened by the tenth, so it shows nine days of current lateness. Its expected finish is recorded beside it.
Example
A customer-approved revised target is tracked without erasing the original baseline. The new date drives the operational plan and customer messages. Management reviews the gap between original and revised dates to learn what happened.
Formula
Calculation
Slippage days = actual completion date - original baseline date. June 22 - June 15 = +7 calendar days, meaning late; a negative figure means early.
Worked example. A fictional team reports five completed onboarding milestones with slippage of +7, 0, +3, +12 and -1 days.
- Total slippage = 7 + 0 + 3 + 12 - 1 = 21 days, so the mean is 21 / 5 = 4.2 days.
- Sorted, the values are -1, 0, 3, 7 and 12, so the median is 3 days; the single +12 case pulls the mean above the median.
- Three of the five milestones were late, so the late share is 3 / 5 x 100 = 60%.
- An overdue milestone still open at +4 days is shown separately as open lateness, not left out.Case study
Seen in the real world.
In this entirely fictional example, Cedar Software sees repeated go-live delays from late data validation. It adds an early sample-data check and explicit customer input deadline, then measures later onboarding cohorts. It keeps the original milestone date in its report even when a new plan is agreed.
Over the next two quarters the team compares median slippage and late share for the new cohorts with those from before the change. It also checks whether the cohorts had a similar mix of simple and complex integrations, so that a change in customer type is not mistaken for an improvement in process. Cedar is an invented company, and its figures are for illustration only.
Watch out
Common mistakes.
- Updating the baseline after every slip so the report always shows zero.
- Marking an internal task complete when the customer-facing milestone is not met.
- Excluding overdue open milestones from a completed-only average.
Questions
People also ask.
Can an approved revised date be used?
Yes for the current plan, while the original baseline stays visible for history.
What counts as completion?
The agreed observable milestone evidence, not a vague status.
Does late mean the delivery team caused it?
No. Check dependencies and the full sequence before assigning cause.
From the founder's library

Take it further with the book.
Build your financial confidence beyond this definition. Shihan's full-length guide, Accounting Fundamentals, takes the same plain-English approach and turns it into a complete, practical playbook for non-finance managers, business owners and students - with chapter-end quiz answers and presentation slides included.
25% off with code MMHQ25, applied at checkout. Priced in USD - checkout may show the equivalent in your local currency.
View the book and save 25%