Back to Glossary

Entry · Business

Preliminaries

In construction, preliminaries are project-wide requirements and associated costs needed to carry out the works but not readily assigned to one measured building item. They can include site management, setup, temporary services and shared facilities.

From the Money Master HQ dictionary, founded by Shihan Sheriff (FCMA, VP of Finance at Nomod, CFO at Esanjo Ventures). How these definitions are written.

What it means

Preliminaries are the project-wide requirements and costs of making the construction work possible on a particular site. A tender prices concrete, walls and finishes, but it also needs a site office, supervision and temporary power to organise that work, and those items may sit in a preliminaries section.

Designing Buildings describes preliminaries as tender requirements and costs linked to the method and circumstances of the works rather than to one package of permanent building work, and scope varies by project. RICS New Rules of Measurement provide guidance for consistent construction cost measurement, and their schedules can help bidders set out preliminaries, though a client's particular tender documents still govern what bidders must include.

A fictional contractor prices site fencing, welfare facilities and a supervisor under preliminaries, and bricks and labour to build walls under the building work. Clear separation helps compare tender submissions.

Some preliminaries are one-off, such as initial site setup, while others depend on duration, such as monthly security or office hire, so label the basis because a delayed project affects them differently. A fictional site has a six-month programme and a supervisor costing $8,000 per month, and if work lasts longer the actual time-related cost can grow, although the right contractual recovery is a separate question.

A listed preliminary does not automatically become an extra payment when the programme changes, because notice, causation, mitigation and valuation rules in the contract matter, so avoid multiplying every monthly item by every extra month without review. Preliminaries can include site safety, environmental protection, common-use plant and cleaning, while some specialist subcontractor costs may instead be embedded in trade rates, so do not double count them.

A fictional builder that hires a crane shared by several trades must decide whether the common-use item sits in preliminaries or within trade prices, and the tender should make the choice clear. A client comparing bids may see one bidder with low preliminaries and higher trade rates, so compare total scope and assumptions rather than a percentage alone.

The ratio of preliminaries to tender price can be useful context but is not a universal benchmark, because project duration, access constraints, logistics and reporting duties change it, and a fixed 8% to 15% rule should not be applied to every tender. A fictional hospital refurbishment that works around live services and patients has different site-management costs from a vacant new-build plot, and the difference can be real rather than an inflated bid.

Preliminaries may also describe non-price requirements, such as programme reporting or approval procedures, which the contractor needs to cost, because a scope omission can become a dispute later. Site overheads are a related cost term, and a company-wide head-office overhead may be treated separately, so identify the particular project costs before comparing them.

A tenderer should read the employer's conditions and estimate actual resources such as staff, site facilities and time, because a guessed percentage can conceal missing items, as a fictional contractor found when its low site-security allowance met a tender that required overnight coverage. When variations occur, check whether they change project-wide requirements, ask bidders to separate fixed and time-related preliminaries, and document what each price includes, since insurance, temporary works and utility charges can overlap with other schedules.

In practice

Real-world examples.

1

Example

A tender lists site offices, fencing and temporary power outside permanent works. The contractor groups them in the preliminaries section so the client can see what it pays to set up the site. The brick and concrete rates then cover only the permanent building work.

2

Example

Monthly supervision is identified as time-related, costing $8,000 a month over a six-month programme. If a client-requested change stretches the programme by a month, the contractor can show the monthly rate behind its claim. Fixed items such as the initial fencing do not grow with the delay.

3

Example

A client checks whether common-use plant, such as a shared tower crane, is included twice. The crane appears once in the preliminaries and again inside the steelwork subcontractor's rates. Removing the duplicate saves the client from paying for the same equipment twice.

Formula

Calculation

Preliminaries share (%) = preliminaries total / tender price base x 100. Name the denominator clearly, and estimate actual items rather than setting a universal percentage. Worked example: a fictional contractor builds up its preliminaries for a six-month programme. Time-related items are supervision at $8,000 a month, site office and welfare hire at $3,000 a month and security at $4,000 a month, a total of $15,000 a month, or 6 x $15,000 = $90,000. Fixed items are site setup and fencing of $30,000 and insurance and temporary services of $20,000, a total of $50,000. Preliminaries total $90,000 + $50,000 = $140,000. Against a tender price base of $1,750,000, the share is $140,000 / $1,750,000 x 100 = 8%. If the programme runs two months late, only the time-related items grow, so the candidate extra cost is 2 x $15,000 = $30,000, and whether it is recoverable depends on the contract.

Case study

Seen in the real world.

In this fictional example, Palm Grove Developments compares three tenders. One bidder has low preliminaries but has placed site services inside trade rates. The client asks all bidders to clarify the same scope before selecting an offer. On a common tender price base of $2,000,000, Bidder A shows preliminaries of $120,000, or 6%, while Bidder B shows $200,000, or 10%.

After clarification, Bidder A confirms that $90,000 of site services sit inside its trade rates, so its true preliminaries are $210,000, or 10.5%. The apparent saving disappears. Palm Grove ends up comparing like with like and selects on total scope, programme and risk allocation. It avoids treating one percentage as proof of value.

Watch out

Common mistakes.

  • Using a fixed percentage without pricing project needs.
  • Double-counting site-wide items in trade rates.
  • Assuming time-related preliminaries are automatically recoverable after delay.

Questions

People also ask.

What can preliminaries include?

Site management, temporary services, shared facilities, safety and other project-wide requirements.

Are they always time-related?

No. Some are fixed or one-off, while others vary with duration.

What is the usual percentage?

There is no universal share; scope, programme and site conditions govern.

Was this explanation helpful?

From the founder's library

Accounting Fundamentals: A Non-Finance Manager's Guide to Finance and Accounting, by Shihan Sheriff

Take it further with the book.

Build your financial confidence beyond this definition. Shihan's full-length guide, Accounting Fundamentals, takes the same plain-English approach and turns it into a complete, practical playbook for non-finance managers, business owners and students - with chapter-end quiz answers and presentation slides included.

US$2.24US$2.99

25% off with code MMHQ25, applied at checkout. Priced in USD - checkout may show the equivalent in your local currency.

View the book and save 25%
Last updated · October 8, 2026
Browse all terms →

Disclaimer

The information provided in this finance dictionary is for educational and informational purposes only. It should not be construed as financial, investment, legal, or tax advice. Always consult with a qualified professional before making any financial decisions. Money Master HQ makes no representations or warranties about the accuracy, completeness, or suitability of this information. Use of this content is at your own risk.