Back to Glossary

Entry · Accounting

Site Overheads

Site overheads are project-site support costs that cannot be assigned neatly to a single construction work item, such as temporary facilities, site supervision, security and utilities. Some vary with time, while others are one-off or activity-based; their treatment depends on the cost plan and contract.

From the Money Master HQ dictionary, founded by Shihan Sheriff (FCMA, VP of Finance at Nomod, CFO at Esanjo Ventures). How these definitions are written.

What it means

A project needs offices, fencing, lighting and supervision to operate, and those costs support many trades at once, so they are often grouped as site overheads or part of preliminaries. RICS measurement guidance addresses how construction costs can be classified and measured, but terminology varies between markets and contracts, so a bidder should use the required schedule and avoid assuming one label covers every item.

Procore's guide to construction preliminaries discusses temporary site facilities, safety and project management, and these costs are essential even though they are not permanent parts of the finished building, with their exact scope following the contract. Some costs are fixed at the start, such as establishing a site office, while others recur monthly, such as utilities and guards, and separating them improves a tender and any later delay analysis.

Site overheads differ from company-wide head-office overheads: a local security contract is site-specific, while corporate finance, rent and leadership may need separate allocation methods. Supervision can be a major time-related cost, so actual staff assigned and their dates should be recorded, and a project manager split between several sites should not be charged in full to each.

The simple formula, monthly running cost times duration, is useful for recurring costs but is not a universal measure of total site overheads, so setup, demobilisation and activity-related items should be added separately. For example, $45,000 per month for 14 months gives $630,000 of recurring cost, and if setup costs $70,000 and site closure costs $20,000, the simple recurring figure is incomplete.

All values are hypothetical. Accurate tendering needs a realistic programme, because longer access restrictions, night work or remote locations can change site support needs, so the delivery plan should be used and not only a generic percentage of construction value.

Procore's general-conditions guidance also discusses site-management and temporary requirements, and different contracts place them under different headings, so bid inclusions should be compared line by line. During delivery, actual site overheads should be compared with the budget, since a variance can reflect delay, overtime, scope change or a poor estimate, and the driver should be investigated before claiming reimbursement.

A delay does not automatically make all site overheads recoverable from a client, because contract provisions, cause and actual additional cost matter, so records should be preserved for a separate entitlement review. Double counting needs avoiding too: if a subcontract price already includes its own site offices, adding the same cost again to the main contractor's support line may inflate the estimate, so scope boundaries should be clarified.

Health and safety support is part of operating a site, so training, protective systems and required facilities should be budgeted rather than treated as optional savings, with requirements varying by location and project. Cash flow also matters, as site setup may be paid before progress billings, so the timing of expenses should be forecast so a project can operate even before revenue catches up.

A clear site-overhead schedule shows each resource, duration, rate and owner, helping price bids, manage costs and explain variations, and the best estimate follows the actual delivery plan.

In practice

Real-world examples.

1

Example

A fictional contractor rents site cabins for a tower project and budgets temporary cabins and site security. The cabins support all trades, not one concrete pour, so the rental sits in the site support budget. A fictional school builder pays to install fencing once and then to maintain it each month, so it builds a line-item forecast instead of multiplying one monthly number.

2

Example

A fictional civil contractor shares one survey manager across two sites. Its cost coding records the days spent on each site, and the estimate is later checked against timesheets. A fictional warehouse job with limited electricity needs temporary generation, so its support cost is higher than a similar job with grid access.

3

Example

A fictional fit-out contractor finds that both its preliminaries and an electrical subcontract include temporary power. It checks which party will provide it and removes the duplicate, and the cost plan then reflects actual responsibility. The tender separates setup costs from monthly running costs.

Formula

Calculation

Illustrative recurring site overhead = supported monthly running cost x months. Add setup, demobilisation and activity-based costs separately. Worked example. A fictional contractor expects recurring site costs of $45,000 per month (cabins, utilities, guards and supervision) over 14 months, so recurring cost is $45,000 x 14 = $630,000. Adding $70,000 of setup and $20,000 of site closure gives a total of $630,000 + $70,000 + $20,000 = $720,000. If the project is delayed by 2 months, the recurring element rises by 2 x $45,000 = $90,000 to $720,000, and the total to $810,000, before any question of who bears the extra cost. All values are hypothetical.

Case study

Seen in the real world.

In this fictional case, North Build estimates a 12-month site with cabins, security and supervision. It records one-off setup and monthly services on different budget lines. When completion slips, it documents which services actually continued and why. It assesses contractual recovery separately from the accounting cost.

The project accountant reviews the budget each month, comparing actual cabin rent, utilities and guard costs with the line items. She flags the supervision line, which has risen because a manager stayed on the project two extra months, and records the cause. North Build is invented for illustration, and the example does not describe any real contract or claim.

Watch out

Common mistakes.

  • Applying one monthly rate to all one-off and recurring costs.
  • Counting head-office and site expenses twice.
  • Assuming every delayed-site cost is recoverable.

Questions

People also ask.

Are site overheads the same as materials?

No. They support the site rather than one direct work item.

Do all overheads rise with time?

No. Some are fixed or linked to particular activities.

Why track them separately?

To improve bids, cost control and any later claim analysis.

Was this explanation helpful?

From the founder's library

Accounting Fundamentals: A Non-Finance Manager's Guide to Finance and Accounting, by Shihan Sheriff

Take it further with the book.

Build your financial confidence beyond this definition. Shihan's full-length guide, Accounting Fundamentals, takes the same plain-English approach and turns it into a complete, practical playbook for non-finance managers, business owners and students - with chapter-end quiz answers and presentation slides included.

US$2.24US$2.99

25% off with code MMHQ25, applied at checkout. Priced in USD - checkout may show the equivalent in your local currency.

View the book and save 25%
Last updated · October 8, 2026
Browse all terms →

Disclaimer

The information provided in this finance dictionary is for educational and informational purposes only. It should not be construed as financial, investment, legal, or tax advice. Always consult with a qualified professional before making any financial decisions. Money Master HQ makes no representations or warranties about the accuracy, completeness, or suitability of this information. Use of this content is at your own risk.